Fairwinds
International, Inc. was requested to assist Century
Exploration of New Orleans with fast-track management
of a new-build concrete production barge facility off the environmentally
sensitive wetlands of the Atchafalaya Basin in Louisiana, USA.
From scheduling through permitting, commissioning and start-up assistance,
Fairwinds was charged with the conceptual and detailed design of the barge,
equipment and pipeline. This included procurement, construction management,
AFE cost controls, vendor surveillance, tow and route delivery analysis, and
site installation.
Due to environmental concerns, studies were conducted for Air Emission Analysis
and Mitigation, Owner's Risk Analysis, Hurricane Storm and Flood Planning,
HAZOP review, Risk Register Maintenance, and Unmanned Reliability and Maintainability
Studies. These studies were used as part of the permitting process with local,
state and federal government agencies to meet regulatory statutes.
In addition, studies were conducted for Operability and SCADA monitoring, human
factor interfaces and safety-in-design.

This project was delivered on-time and well within budget constraints and is
currently producing at owner's expectations. A new offset well is planned to
tie-back to the barge production facility which was designed with sufficient
spare capacities.
Only four months elapsed between logging the discovery well until production
commenced through the new barge facility and lateral pipeline.
|